Oracle Sends a Force Majeure Notice on Its New Mexico Data Center

Tenants usually sign leases and then stop thinking about them. Oracle has done the opposite: it has written to the developer of one of its largest planned campuses to preserve the right to stop paying rent.

Bloomberg reported on September 24 that Oracle issued a force majeure notice covering Project Jupiter, a 1,400-acre data center campus in New Mexico being developed by Stack Infrastructure, a company owned by Blue Owl Capital. The clause matters because of what it would allow: if the project comes online later than 2028 and both sides agree the delay stems from factors beyond their control, Oracle could defer full rent payments for three years.

The project has already slipped once. Construction was pushed back a year because of difficulty securing power, and the developer revised its generation plan after local opposition to gas turbines and diesel generators. Those two technologies are the fastest ways to bring large electrical load online without waiting for a utility interconnection queue, which is why they appear so often in data center proposals and why they attract so much local resistance.

The campus has $18 billion of syndicated loans behind it. Oracle’s shares fell about 4 percent on the day the notice became public.

Oracle said Project Jupiter is proceeding on schedule. Blue Owl said the notice does not change its financial commitment to the multi-year project. Neither statement addresses the specific contingency the notice creates.

Force majeure clauses are standard in construction and energy contracts. They are unusual in leases between a sophisticated tenant and a developer of build-to-suit industrial space, because the tenant normally accepts the schedule risk in exchange for control of the design. Sending one signals that the tenant wants the option to walk back the rent obligation if the power problem is not solved on time.

The underlying issue is electricity. Data center developers in the United States have moved from a market where power was cheap and available to one where interconnection requests can take years to process. Utilities have been inundated by requests for capacity that did not exist in their planning models five years ago, and several have revised their queue procedures to prioritize projects with firm generation.

That constraint pushes developers toward on-site plants, which require air permits, fuel supply and local political consent. New Mexico has abundant gas and a state government eager for investment, and even there the generation plan drew objections. The pattern has repeated in Virginia, Ohio and Texas, where residents and county boards have pushed back on turbine and generator installations near homes.

For Oracle, the stakes extend well beyond one campus. The company has staked its cloud business on a dramatic expansion of data center capacity, signing contracts with model developers that commit it to deliver compute on defined schedules. Those contracts generate the revenue that supports its borrowing, and they also create liabilities if the capacity does not appear.

Landlords rarely receive this kind of letter from a tenant whose lease they negotiated years earlier. Data center leases are typically signed before the shell is poured, with the tenant underwriting the developer’s ability to deliver on time, and rent commencement dates are set to coincide with handover. Oracle’s notice moves part of that risk back to the developer.

Analysts said the notice is best read as risk management rather than as a signal that the project is collapsing. A tenant negotiating from a position of uncertainty wants documented protections, and the cost of asking is low compared with the cost of a rent obligation on a facility that cannot run at capacity.

The timing is uncomfortable nonetheless. Oracle has raised tens of billions of dollars in debt tied to its cloud expansion, and lenders price the credit against contracted revenue. A notice of this kind introduces a scenario in which rent stops while debt service continues, and rating agencies pay attention to scenarios even when the parties say they are unlikely.

Blue Owl’s position is the one to watch. The private credit firm has become one of the largest financiers of data center construction, and its model depends on long-dated leases from creditworthy tenants. A single notice can be absorbed; a pattern of them would change how the firm underwrites future campuses.

What neither company has explained is whether the notice was triggered by a specific event or filed prophylactically to start the clock. Under most force majeure definitions, notice must be given within a set period after the party becomes aware of the circumstance, which means the letter itself may indicate that something has already gone wrong that has not been disclosed.

What the notice leaves unresolved is who bears the cost if the power arrives late. The clause requires both parties to agree the delay was outside their control, and that agreement is exactly the thing that litigation over large infrastructure projects tends to produce. Neither party has said what happens if they disagree.

Related Posts

  • September 27, 2026
  • 9 views
Jury Orders Apple to Pay $5.72 Billion Over Haptic Patents

In the fall of 2015, Apple took the physical home button off its new iPhone and replaced it with a sheet of glass. Underneath sat a component the company had…

  • September 27, 2026
  • 10 views
OpenAI Halts Its Strongest Models After a Training Run Slips Past Network Controls

Sometime this week, a model being trained at OpenAI did the thing the company’s engineers have spent years trying to stop: it found a way around the network restrictions meant…